| DE3723795A |
The invention relates to the field of stay cable system for cable-stayed bridges.
Stay cable system consists basically of tendon member, protection member, the member of anchorage sockets as well as the member of cable-girder and cable-pylon attaching structures. These members relate and influence with each other. Stay cables normally govern the useful life and construction progress of cable-stayed bridges with the following factors: resistance to fatigue loading and corrosion, ease of transportation and erection, allowance of inspecting as well as ability of eventual replacement. The attaching structures influence the safety, economy and aesthetics of whole bridge sensitively by the reliability and compact of their arrangement.
DE 3 723 795 A discloses a stay cable system with all the features of the preamble of claim 1.
The tendons with parallel strands are more and more widely used in stay cable systems, because of their advantages of easy transportation and erection. But at present there are three serious problems in such kind of cable systems.
Two types of anchorage socket are now currently used for such kind of cables:
At present the most current corrosion protecting method for such kind of cables is to cover the individual multilayer protected strands by a sheath pipe [Brochure: Freyssinet STAY CABLES MAY 1994 p.14, Fig.22], [Brochure: VSL STAY CABLE SYSTEM 200 SSI section "Corrosion Protection" and "Outer Stay Pipe"]. Easy to erect and replace strands is the main advantage of this method. But a great problem of the method is that if there is water and moisture inside sheath pipe, it is difficult to discover them and clear them away. It is necessary that water and moisture inside sheath pipe can be surveyed and cleared away.
In concrete cable-stayed bridges, web thickness of girder is usually bigger than diameter of cable anchorage head, so, cable anchorage socket is easy to go through the girder web and to be reliably anchored at the bottom of the girder. In composite cable-stayed bridges, web thickness of steel I-girder, which is the most economical type of steel girder, is much smaller than diameter of cable anchorage head, so, attaching structures become complicated. At present three imperfect types of attaching structure are normally used in composite cable-stayed bridges:
This invention will solve the entire Problem A, Problem B and Problem C at the same time.
Figure 1 illustrates the general layout of the novel stay cable system, which is exclusively for the tendons with parallel strands (I) covered by a sheath pipe (Ib). The system comprises five parts:
Anchoring holes in the socket are divided into two symmetrical groups. Axis of two symmetrical groups of strands (I) and the centre plane of web(s) of any kind of girders (II or IId) can coincide while the socket can be arranged under the bottom of the girders.
It comprises a pair of half-cylindrical anchorage sockets arranged on both sides of the web in steel I-girder (II), in anchoring tie beam (3) or in steel anchoring bed (4). In the sockets (2) strands can individually be anchored or bonded to withstand fatigue loading.
In current stay cable system with parallel strands, monostrand anchored holes on anchor head are normally arranged with odd number (for example 61). In this invention (see Figure2), monostrand anchored holes on main anchor head (1) are always arranged with even number (for example 60), and are separated into two symmetrical groups (1a and 1b). The minimum central distance Dg between the two groups of holes is Dg = Tw (thickness of web IIa of steel I-girder II) + Dh (diameter of monostrand anchored hole 2c and 2d in auxiliary anchorage sockets 2a and 2b) + 2At (thickness of inside wall of auxiliary anchorage sockets 2a and 2b). Thus, those two groups of strand (Ie and If) can easily pass through the I-girder (II) along both side of girder web respectively keeping axes of cable and girder web in a same plane then can reliably be anchored in a main anchor head (1) under the bottom of the girder (II). In pylon anchoring room, the strands (Ia) outside main anchorage socket (see Figure 1) do not be cut off after the final jacking, for it will be convenient for eventual individual strand replacement and the strands will be under protecting of dehumidification system (see Part 5).
Advantages of such arrangement are:
As mentioned above, within the area of girder web and stiffening steel plates, there is plenty of space to arrange fatigue resistant facilities-auxiliary anchorage sockets, which will help the main anchorage socket to withstand fatigue load (see Figure 2). Consequently, it becomes sufficiently safe to use ordinary jaws in main anchorage socket. Since auxiliary anchorage socket works for traffic load only, its construction ought and can be calmly arranged after the final cable force adjustment
Besides the fatigue resistant criterion, another design criterion for auxiliary anchorage sockets is that strands must be individually anchored in the sockets to ensure the possibility of individual strand replacement. Two types of auxiliary anchorage socket are created for selecting.
Structure of the socket is showed in Figure 3 and Figure 4. In the socket there are auxiliary jaws (2j) with smaller bevel angle to anchor strands individually. Edge of teeth on auxiliary jaw is circular to prevent injury and big stress concentration on the anchored strand (I).
Structure of the socket is showed in Figure 5 and Figure 6. In the socket (2a 2 ) there are coned holes for each individual strands. Epoxy, zinc powder and quartz sand mixture (2q) is injected into the coned holes after the final tensioning of cable.
In order to arrange the double half cylindrical auxiliary anchorage sockets, anchoring tie beams in pylon (III) can be simplified to the most economical type of I-beam (3), web and stiffening plates of which are also signed with (IIa) (IIb) respectively as in I-girder. The structures mentioned in Part 1 and Part 2 are valid in Part 3. Tie beam with I-section can be extensively used for inclined cable plane by the helping of tie bars (3a) (see Figure 6).
Advantages of the structure are:
In case the girders (IId) other than steel I-girder or the anchoring structures in pylon (III) other than tie beam are adopted and in order to arrange the double half cylindrical auxiliary anchorage sockets, the conventional anchoring bed can be replaced by a novel steel anchoring bed (4), web and stiffening plates of which are also signed with (IIa) (IIb) respectively as in I-girder (see Figure 8). The structures mentioned in Part 1 and Part 2 are valid in Part 4.
Compare with the conventional concrete anchoring bed, advantage of such anchoring bed is that it can simplify the form work of anchoring zone in concrete pylon, therefore mass of pylon top and construction period can be reduced.
Dehumidification system has been successfully used on Lillebaelt bridge since 1972. Now the system is being used on more and more bridges to protect steel box girders, saddles and anchoring blocks [Book: East Bridge, The Storebaelt Publications, 1998, P.374,375]. Similar principle is adopted for this novel cable protection system (see Figure 9).
Two dry air transmission pipes (5b) are erected from the main anchorage plate (4a) in pylon (III) to the cells enclosed by stiffening plates (IIb) and cover plates (IIc) at the bottom of girder (II or IId) and connected to a dehumidification plant (5g), which is installed inside anchoring room at pylon top, by the dry air entrances (5a). When the dehumidification plant (5g) works, air circulates within the whole hollow part of cable. Dry air is blown into the transmission pipes (5b) through dry air entrances (5a), then separates out of dry air exits (5c) mainly at the bottom of sheath pipe (Ib), partly at the guide pipes (Ic) and cells enclosed by stiffening plates (IIb) and cover plates (IIc). At the same time wet air is exhausted out of cable to the plant (5g) through vent holes (5d), vent pipes (5e), which pass through the positioners (Id) of strands (I) in guide pipe (Ic), and wet air exits (5f). Such operation offers to one cable after another with certain hours per day or per couple of days for each cable. Similar operation offers also to anchoring room in pylon by dry air exit (5o) and wet air entrance (5p) of the plant (5g) at regular intervals to protect the strands (Ia) outside main anchorage socket (see Part 1 also).
Water concentrates usually at the lowest part of cable and moisture concentrates usually at the highest part of cable. Therefore, strand sample (5k) and humidity measuring point (5i) are arranged in the cells enclosed by stiffening plates (IIb) and cover plates (IIc) at the bottom of girder (II or IId), while strand sample (5l) and humidity measuring point (5h) are arranged in the similar cells in pylon (III) respectively. Strand sample (5k) and/or strand sample (5l) can be checked and tested in laboratory, when necessary. Similar checking and testing can be arranged for sample (5n) of the strands (Ia) outside main anchorage socket. Humidity measuring point (5h) can be connected to the automatic control system of dehumidification plant (5g), if necessary. If there is water inside hollow part of cable, it will flow down through drainage holes (5j) and can be pumped out through the drainage valve (5m).
Advantages of this cable protection system are: