Claims:
The invention claimed is:
1. A method for determining optimality of a planned operation schedule comprising the steps of: obtaining said planned operation schedule; obtaining an operation completion time; determining a planned operation schedule variance from said planned operation schedule and said operation completion time; and determining an optimality index as a function of said operation schedule variance.
2. The method of claim 1 further comprising the steps of: obtaining a forecasted operation schedule; determining a forecasted operation schedule variance from said forecasted operation schedule and said operation completion time; and determining said optimality index as a function of said forecasted schedule variance.
3. The method of claim 1 wherein said planned operation schedule is a master production schedule as calculated by a program executed on a computer system.
4. The method of claim 1 wherein the forecasted operation schedule is a forecasted order date, which is a predicted date at which a customer is expected to require a product.
5. The method of claim 1 wherein the operation completion date is an order confirmed date indicating completion of fabrication of the product.
6. The method of claim 1 wherein the planned operation schedule variance is determined by a formula: 33 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
7. The method of claim 2 wherein the planned operation schedule variance is determined by a formula: 34 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
8. The method of claim 2 wherein the forecasted operation schedule variance is determined by a formula: 35 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and n is a quantity of each operation i with n operation counts.
9. The method of claim 2 wherein the optimality index is determined by a formula: 36 where: MPSOI is the optimality index, D1 is the planned operation schedule variance, and D2 is the forecasted operation schedule variance.
10. The method of claim 1 further comprising the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
11. The method of claim 10 wherein the planned operation schedule variance is determined by a formula: 37 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i; pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
12. The method of claim 2 further comprising the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
13. The method of claim 12 wherein the planned operation schedule variance is determined by a formula: 38 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
14. The method of claim 12 wherein the forecasted operation schedule variance is determined by a formula: 39 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
15. The method of claim 1 wherein the optimality index is a concentration/dispersion factor of the operation schedule variance.
16. The method of claim 15 wherein the concentration/dispersion factor is determined by a formula: Z=A32−(A1{overscore (X1)})·(A2{overscore (X2)}) where: Z is the concentration/dispersion factor, A1 is a fraction of a distribution of the planned operation schedule variance greater than an operation completion time tolerance, said operation completion time tolerance being a tolerance of said operation completion times for multiple operations, A2 is a fraction of the distribution of planned operation schedule variance less than the operation completion time tolerance, A3 is a fraction of the distribution of planned operation schedule variance within the operation completion time tolerance, {overscore (X1)} is the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance, and {overscore (X2)} is the mean of the distribution of planned operation schedule variance less than the operation completion time tolerance.
17. The method of claim 16 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 40 where: ylead is a magnitude of planned operation schedule variance for the planned operations having an operation completion time less than the operation completion time tolerance, and x is a planned operation schedule variance.
18. The method of claim 16 wherein the fraction of a distribution of planned operation schedule variance less than an operation completion time variance is determined by a formula: 41 where: ylag is a magnitude of planned operation schedule variance for the planned operations having an operation completion time greater than the operation completion time tolerance, and x is a planned operation schedule variance.
19. The method of claim 16 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 42 where: y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
20. The method of claim 16 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 43 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
21. The method of claim 16 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 44 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
22. An apparatus for determining optimality of a planned operation schedule comprising: means for obtaining said planned operation schedule; means for obtaining an operation completion time; means for determining a planned operation schedule variance from said planned operation schedule and said operation completion time; and means for determining an optimality index as a function of said operation schedule variance.
23. The apparatus of claim 22 further comprising: means for obtaining a forecasted operation schedule; means for determining a forecasted operation schedule variance from said forecasted operation schedule and said operation completion time; and means for determining said optimality index as a function of said forecasted schedule variance.
24. The apparatus of claim 22 wherein said planned operation schedule is a master production schedule as calculated by a program executed on a computer system.
25. The apparatus of claim 23 wherein the forecasted operation schedule is a forecasted order date, which is a predicted date at which a customer is expected to require a product.
26. The apparatus of claim 22 wherein the operation completion date is an order confirmed date indicating completion of fabrication of the product.
27. The apparatus of claim 22 wherein the means for determining the planned operation schedule variance provides a solution for a formula: 45 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
28. The apparatus of claim 23 wherein the means for determining the planned operation schedule variance provides a solution for a formula: 46 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
29. The apparatus of claim 23 wherein means for determining the forecasted operation schedule variance provides a solution for a formula: 47 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and n is a quantity of each operation i with n operation counts.
30. The apparatus of claim 23 wherein the means for determining the optimality index provides a solution for a formula: 48 where: MPSOI is the optimality index, D1 is the planned operation schedule variance, and D2 is the forecasted operation schedule variance.
31. The apparatus of claim 22 further comprising: means for obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
32. The apparatus of claim 31 wherein the means for determining the planned operation schedule variance provides a solution for a formula: 49 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
33. The apparatus of claim 23 further comprising: means for obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
34. The apparatus of claim 33 the means for determining the planned operation schedule variance provides a solution for a formula: 50 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
35. The apparatus of claim 33 wherein means for determining the forecasted operation schedule variance provides a solution for a formula: 51 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
36. The apparatus of claim 22 wherein the optimality index is a concentration/dispersion factor of the operation schedule variance.
37. The apparatus of claim 36 wherein the means for determining the optimality index provides a solution for a formula: Z=A32−(A1{overscore (X1)})·(A2{overscore (X2)}) where: Z is the concentration/dispersion factor, A1 is a fraction of a distribution of the planned operation schedule variance greater than an operation completion time tolerance, said operation completion time tolerance being a tolerance of said operation completion times for multiple operations, A2 is a fraction of the distribution of planned operation schedule variance less than the operation completion time tolerance, A3 is a fraction of the distribution of planned operation schedule variance within the operation completion time tolerance, {overscore (X1)} is the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance, and {overscore (X2)} is the mean of the distribution of planned operation schedule variance less than the operation completion time tolerance.
38. The apparatus of claim 37 the means for determining the optimality index generates the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance by providing a solution for a formula: 52 where: ylead is a magnitude of planned operation schedule variance for the planned operations having an operation completion time less than the operation completion time tolerance, and x is a planned operation schedule variance.
39. The apparatus of claim 37 wherein the means for determining the optimality index generates the fraction of a distribution of planned operation schedule variance less than an operation completion time variance by providing a solution for a formula: 53 where: ylag is a magnitude of planned operation schedule variance for the planned operations having an operation completion time greater than the operation completion time tolerance, and x is a planned operation schedule variance.
40. The apparatus of claim 37 wherein the means for determining the optimality index generates the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance by providing a solution for a formula: 54 where: y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
41. The apparatus of claim 37 wherein the means for determining the optimality index generates the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance by providing a solution for a formula: 55 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
42. The apparatus of claim 37 wherein the means for determining the optimality index the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance by providing a solution for a formula: 56 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
43. A calculating device for determining optimality of a planned operation schedule comprising: a connection to a planned operation scheduling generator for obtaining said planned operation schedule; a connection to a manufacturing information database for obtaining an operation completion time; and a first variance calculator for determining a planned operation schedule variance from said planned operation schedule and said operation completion time.
44. The device of claim 43 further comprising: a connection to a marketing database for obtaining a forecasted operation schedule; a second variance calculator determining a forecasted operation schedule variance from said forecasted operation schedule and said operation completion time; and a third variance calculator connected to the first and second variance calculators determining an optimality index as a function of said operation schedule variance to said forecasted schedule variance.
45. The calculating device of claim 43 wherein said planned operation schedule is a master production schedule as calculated by a program executed on a computer system.
46. The calculating device of claim 44 wherein the forecasted operation schedule is a forecasted order date a predicted date at which a customer is expected to require a product.
47. The calculating device of claim 43 wherein the operation completion date is an order confirmed date indicating completion of fabrication of the product.
48. The calculating device of claim 43 wherein the first variance calculator determines the planned operation schedule variance by providing a solution for a formula: 57 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
49. The calculating device of claim 44 wherein the first variance calculator determines the planned operation schedule variance by providing a solution for a formula: 58 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
50. The calculating device of claim 44 wherein the second variance calculator determines the forecasted operation schedule variance by providing a solution for a formula: 59 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and n is a quantity of each operation i with n operation counts.
51. The calculating device of claim 44 wherein the third variance calculator determines the optimality index by providing a solution for a formula: 60 where: MPSOI is the optimality index, D1 is the planned operation schedule variance, and D2 is the forecasted operation schedule variance.
52. The calculating device of claim 43 wherein the first variance calculator determines the planned operation schedule variance by providing a solution for a formula: 61 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
53. The calculating device of claim 44 wherein the first variance calculator determines the planned operation schedule variance by providing a solution for a formula: 62 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
54. The calculating device of claim 44 wherein the second variance calculator determines the forecasted operation schedule variance by providing a solution for a formula: 63 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
55. The calculating device of claim 43 wherein the optimality index is a concentration/dispersion factor of the operation schedule variance.
56. The calculating device of claim 55 wherein the third variance calculator determines the concentration/dispersion factor by providing a solution for a formula: Z=A32−(A1{overscore (X1)})·(A2{overscore (X2)}) where: Z is the concentration/dispersion factor, A1 is a fraction of a distribution of the planned operation schedule variance greater than an operation completion time tolerance, said operation completion time tolerance being a tolerance of said operation completion times for multiple operations, A2 is a fraction of the distribution of planned operation schedule variance less than the operation completion time tolerance, A3 is a fraction of the distribution of planned operation schedule variance within the operation completion time tolerance, {overscore (X1)} is the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance, and {overscore (X2)} is the mean of the distribution of planned operation schedule variance less than the operation completion time tolerance.
57. The calculating device of claim 56 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 64 where: ylead is a magnitude of planned operation schedule variance for the planned operations having an operation completion time less than the operation completion time tolerance, and x is a planned operation schedule variance.
58. The calculating device of claim 56 wherein the fraction of a distribution of planned operation schedule variance less than an operation completion time variance is determined by a formula: 65 where: ylag is a magnitude of planned operation schedule variance for the planned operations having an operation completion time greater than the operation completion time tolerance, and x is a planned operation schedule variance.
59. The calculating device of claim 56 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 66 where: y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
60. The calculating device of claim 56 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 67 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
61. The calculating device of claim 56 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 68 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
62. A computing system in communication with a marketing database, a manufacturing information database and a planned operation scheduling generator, said computing system executing a wherein the program process for determining optimality of a planned operation schedule comprising the steps of: obtaining said planned operation schedule; obtaining an operation completion time; determining a planned operation schedule variance from said planned operation schedule and said operation completion time; and determining an optimality index as a function of said operation schedule variance.
63. The computing system of claim 62 wherein said wherein the program process further comprises the steps of: obtaining a forecasted operation schedule; determining a forecasted operation schedule variance from said forecasted operation schedule and said operation completion time; and determining said optimality index as a function of said forecasted schedule variance.
64. The computing system of claim 62 wherein said planned operation schedule is a master production schedule as calculated by a program executed on a computer system.
65. The computing system of claim 62 wherein the forecasted operation schedule is a forecasted order date, which is a predicted date at which a customer is expected to require a product.
66. The computing system of claim 62 wherein the operation completion date is an order confirmed date indicating completion of fabrication of the product.
67. The computing system of claim 62 wherein the program process determines the planned operation schedule variance by solving a formula: 69 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
68. The computing system of claim 63 wherein the program process determines the planned operation schedule variance by solving a formula: 70 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
69. The computing system of claim 63 wherein the program process determines the forecasted operation schedule variance by solving a formula: 71 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and n is a quantity of each operation i with n operation counts.
70. The computing system of claim 63 wherein the wherein the program process determines the optimality index by solving a formula: 72 where: MPSOI is the optimality index, D1 is the planned operation schedule variance, and D2 is the forecasted operation schedule variance.
71. The computing system of claim 62 wherein the wherein the program process further comprises the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
72. The computing system of claim 71 wherein the program process determines the planned operation schedule variance by solving a formula: 73 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
73. The computing system of claim 63 wherein the wherein the program process further comprises the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
74. The computing system of claim 73 wherein the wherein the program process determines the planned operation schedule variance by solving a formula: 74 where: D1 is the planned operation schedule variance MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
75. The computing system of claim 73 wherein the wherein the program process determines the forecasted operation schedule variance by solving a formula: 75 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
76. The computing system of claim 62 wherein the optimality index is a concentration/dispersion factor of the operation schedule variance.
77. The computing system of claim 76 wherein the wherein the program process determines the concentration/dispersion factor by solving a formula: Z=A32−(A1{overscore (X1)})·(A2{overscore (X2)}) where: Z is the concentration/dispersion factor, A1 is a fraction of a distribution of the planned operation schedule variance greater than an operation completion time tolerance, said operation completion time tolerance being a tolerance of said operation completion times for multiple operations, A2 is a fraction of the distribution of planned operation schedule variance less than the operation completion time tolerance, A3 is a fraction of the distribution of planned operation schedule variance within the operation completion time tolerance, {overscore (X1)} is the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance, and {overscore (X2)} is the mean of the distribution of planned operation schedule variance less than the operation completion time tolerance.
78. The computing system of claim 77 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 76 where: ylead is a magnitude of planned operation schedule variance for the planned operations having an operation completion time less than the operation completion time tolerance, and x is a planned operation schedule variance.
79. The computing system of claim 77 wherein the fraction of a distribution of planned operation schedule variance less than an operation completion time variance is determined by a formula: 77 where: ylag is a magnitude of planned operation schedule variance for the planned operations having an operation completion time greater than the operation completion time tolerance, and x is a planned operation schedule variance.
80. The computing system of claim 77 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 78 where: y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
81. The computing system of claim 77 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 79 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
82. The computing system of claim 77 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 80 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
83. A medium for retaining a computer program which, when implemented by a computing system, executes a process for determining optimality of a planned operation schedule, said process comprising the steps of: obtaining said planned operation schedule; obtaining an operation completion time; determining a planned operation schedule variance from said planned operation schedule and said operation completion time; and determining an optimality index as a function of said operation schedule variance.
84. The medium of claim 83 wherein said process further comprises the steps of: obtaining a forecasted operation schedule; determining a forecasted operation schedule variance from said forecasted operation schedule and said operation completion time; and determining said optimality index as a function of said forecasted schedule variance.
85. The medium of claim 83 wherein said planned operation schedule is a master production schedule as calculated by a program executed on a computer system.
86. The medium of claim 83 wherein the forecasted operation schedule is a forecasted order date, which is a predicted date at which a customer is expected to require a product.
87. The medium of claim 83 wherein the operation completion date is an order confirmed date indicating completion of fabrication of the product.
88. The medium of claim 83 wherein the process determines the planned operation schedule variance by solving a formula: 81 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
89. The medium of claim 84 wherein the process determines the planned operation schedule variance by solving a formula: 82 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, n is a quantity of each operation i with n operation counts.
90. The medium of claim 84 wherein the process determines the forecasted operation schedule variance by solving a formula: 83 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and n is a quantity of each operation i with n operation counts.
91. The medium of claim 84 wherein the process determines the optimality index by solving a formula: 84 where: MPSOI is the optimality index, D1 is the planned operation schedule variance, and D2 is the forecasted operation schedule variance.
92. The medium of claim 83 wherein the process further comprises the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
93. The medium of claim 92 wherein the process determines the planned operation schedule variance by solving a formula: 85 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDI is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
94. The medium of claim 84 wherein the process further comprises the step of: obtaining a penalty factor, said penalty factor incurred for not meeting said planned operation schedule.
95. The medium of claim 94 wherein the process determines the planned operation schedule variance by solving a formula: 86 where: D1 is the planned operation schedule variance, MPSDatei is the planned operation schedule for operation i, OCDi is the operation completion date for the operation i, pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
96. The medium of claim 94 wherein the process determines the forecasted operation schedule variance by solving a formula: 87 where: D2 is the forecasted operation schedule variance, FODi is the forecasted operation schedule for operation i, OCDi is the operation completion date for the operation i, and pi is the penalty factor for operation i having missed the operation completion date. n is a quantity of each operation i with n operation counts.
97. The medium of claim 83 wherein the optimality index is a concentration/dispersion factor of the operation schedule variance.
98. The medium of claim 97 wherein the process determines the concentration/dispersion factor by solving a formula: Z=A32−(A1{overscore (X1)})·(A2{overscore (X2)}) where: Z is the concentration/dispersion factor, A1 is a fraction of a distribution of the planned operation schedule variance greater than an operation completion time tolerance, said operation completion time tolerance being a tolerance of said operation completion times for multiple operations, A2 is a fraction of the distribution of planned operation schedule variance less than the operation completion time tolerance, A3 is a fraction of the distribution of planned operation schedule variance within the operation completion time tolerance, {overscore (X1)} is the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance, and {overscore (X2)} is the mean of the distribution of planned operation schedule variance less than the operation completion time tolerance.
99. The medium of claim 98 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 88 where: ylead is a magnitude of planned operation schedule variance for the planned operations having an operation completion time less than the operation completion time tolerance, and x is a planned operation schedule variance.
100. The medium of claim 98 wherein the fraction of a distribution of planned operation schedule variance less than an operation completion time variance is determined by a formula: 89 where: ylag is a magnitude of planned operation schedule variance for the planned operations having an operation completion time greater than the operation completion time tolerance, and x is a planned operation schedule variance.
101. The medium of claim 98 wherein the fraction of a distribution of planned operation schedule variance greater than an operation completion time variance is determined by a formula: 90 where: y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
102. The medium of claim 98 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 91 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.
103. The medium of claim 98 wherein the mean of the distribution of the planned operation schedule variance greater than the operation completion time tolerance is determined by a formula: 92 y is a magnitude of planned operation schedule variance for the planned operations having an operation completion time within the operation completion time tolerance, and x is a planned operation schedule variance.